We require the consultants to specify fill requirements on their general notes page on their detailed engineering (construction) plans, as follows:
FILLING OF ALL PROPERTIES AND ROAD RESERVES MUST BE CARRIED OUT USING APPROVED FILL. TOPSOIL AND ALL VEGETABLE MATTER MUST BE STRIPPED FROM THE SITE PRIOR TO FILLING. ALL FILLING TO BE CARRIED OUT IN 150MM LAYERS AND COMPACTED TO 95% MAXIMUM DRY DENSITY TO COMPLY WITH AS3798-2007, SECTION 8.2, LEVEL 1 AND A FILL REPORT MUST BE PROVIDED FROM A NATA REGISTERED SOIL TESTING LABORATORY.
Hope this helps. If you need more info, you can contact me on 03 9742 0798 or email on
Julian.farrugia@wyndham.vic.gov.au.
Cheers,
-------------------------------------------
Julian Farrugia
Wyndham City Council
WERRIBEE VIC
-------------------------------------------
Original Message:
Sent: 09-07-2015 22:55
From: Clare Hamilton
Subject: Quality Assurance - Fill
Hi all
Was just wondering what everyone asks for in terms of quality assurance for earth fill?
-------------------------------------------
Clare Hamilton
Development Engineer
Selwyn District Council
Rolleston
-------------------------------------------